Anniversary of 15 MW Solar Power Park Using Seraphim Modules

Recently, the biggest solar project in India using Seraphim modules has been successfully running one year; this 15MW project locates in Karur District, Tamil Nadu, and the project is installed in phases, the first phase of the project (5 MW) was commissioned in a very short time period of 70 days and the entire15 MW project was completed in 82 days from start to finish.

The Solar panels used are high efficiency 250/255 Wp EzBox™ panels, with Thresher Certificate (triple IEC61215+61730 certification) and Chubb insurance for the power generation. This is the first time that Seraphim’s EzBox™ modules used in India; it will be widely accepted by customers in the foreseeable future, because of its great benefits to developers and EPC companies from both time and cost.